Verified Competency Register for Simon Sheehan

=Method Group

More information about this page | Visit www.methodcompreg.com

Login to view account

To access this account please enter the password below. this password will be available from Simon only.


61511

Task Level of
Competency
Date Verification
Status
61511-FSM | Functional Safety ManagementMore informationAs Technical Authority for Petroineos UK and previously as SIS Project Engineer for Petroineos Refinery, Simon has led the construction and commissioning phases of many SIS related projects up to the value of £8M. These projects ranged from the introduction of single new SIFs to existing systems to complete logic solver replacement projects. Simon has led the construction and commissioning teams, developing commissioning strategies & energisation plans for projects and formally accepted installation and commissioning as complete for major projects for Petroineos. In 2019 Simon wrote a new test & commissioning standard for all Petroineos UK sites following BS EN 62381-2012. Simon has led installation and commissioning on a number of complex projects involving modifying online logic solvers and complex intertrip systems and live cut overs, all on systems protecting running plant. Master 2021-01-15
Verified
Pending
Initial Assessment 
61511-FSM | Functional Safety ManagementMore informationAs Technical Authority for Petroineos UK and previously as SIS Project Engineer for Petroineos Refinery, Simon has led the construction and commissioning phases of many SIS related projects up to the value of £8M. These projects ranged from the introduction of single new SIFs to existing systems to complete logic solver replacement projects. Simon has led the construction and commissioning teams, developing commissioning strategies & energisation plans for projects and formally accepted installation and commissioning as complete for major projects for Petroineos. In 2019 Simon wrote a new test & commissioning standard for all Petroineos UK sites following BS EN 62381-2012. Simon has led installation and commissioning on a number of complex projects involving modifying online logic solvers and complex intertrip systems and live cut overs, all on systems protecting running plant. Master 2021-01-15
Verified
Pending
Initial Assessment 
61511-FSM | Functional Safety ManagementMore informationAs Technical Authority for Petroineos UK and previously as SIS Project Engineer for Petroineos Refinery, Simon has led the construction and commissioning phases of many SIS related projects up to the value of £8M. These projects ranged from the introduction of single new SIFs to existing systems to complete logic solver replacement projects. Simon has led the construction and commissioning teams, developing commissioning strategies & energisation plans for projects and formally accepted installation and commissioning as complete for major projects for Petroineos. In 2019 Simon wrote a new test & commissioning standard for all Petroineos UK sites following BS EN 62381-2012. Simon has led installation and commissioning on a number of complex projects involving modifying online logic solvers and complex intertrip systems and live cut overs, all on systems protecting running plant. Master 2021-01-15
Verified
Pending
Initial Assessment 
61511-FSM | Functional Safety ManagementMore informationAs Technical Authority for Petroineos UK and previously as SIS Project Engineer for Petroineos Refinery, Simon has led the construction and commissioning phases of many SIS related projects up to the value of £8M. These projects ranged from the introduction of single new SIFs to existing systems to complete logic solver replacement projects. Simon has led the construction and commissioning teams, developing commissioning strategies & energisation plans for projects and formally accepted installation and commissioning as complete for major projects for Petroineos. In 2019 Simon wrote a new test & commissioning standard for all Petroineos UK sites following BS EN 62381-2012. Simon has led installation and commissioning on a number of complex projects involving modifying online logic solvers and complex intertrip systems and live cut overs, all on systems protecting running plant. Master 2021-01-15
Verified
Pending
Initial Assessment 
61511-FSM | Functional Safety ManagementMore informationAs Technical Authority for Petroineos UK and previously as SIS Project Engineer for Petroineos Refinery, Simon has led the construction and commissioning phases of many SIS related projects up to the value of £8M. These projects ranged from the introduction of single new SIFs to existing systems to complete logic solver replacement projects. Simon has led the construction and commissioning teams, developing commissioning strategies & energisation plans for projects and formally accepted installation and commissioning as complete for major projects for Petroineos. In 2019 Simon wrote a new test & commissioning standard for all Petroineos UK sites following BS EN 62381-2012. Simon has led installation and commissioning on a number of complex projects involving modifying online logic solvers and complex intertrip systems and live cut overs, all on systems protecting running plant. Master 2021-01-15
Verified
Pending
Initial Assessment 
61511-SRS | Safety Requirement Specification Master 2021-11-14
Verified
Pending
Initial Assessment 
61511-SRS | Safety Requirement Specification Master 2021-11-14
Verified
Pending
Initial Assessment 
61511-FSA1 | Stage 1 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos UK, Simon has carried out several ad-hoc FSA1's as part of FSA5, albeit on very minor modifications, and generally only with impact on LOPA and SRS documentation rather than HAZOP/PHA documentation. As part of this role Simon has accepted many FSA1 reports for Petroineos. Simon has carried out 1 FSA1 in another role on behalf of a North Sea operator, which did include a review of HAZOP documentation. This project included the addition of 4 new SIFs. Professional 2021-02-12
Verified
Pending
Initial Assessment 
61511-FSA1 | Stage 1 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos UK, Simon has carried out several ad-hoc FSA1's as part of FSA5, albeit on very minor modifications, and generally only with impact on LOPA and SRS documentation rather than HAZOP/PHA documentation. As part of this role Simon has accepted many FSA1 reports for Petroineos. Simon has carried out 1 FSA1 in another role on behalf of a North Sea operator, which did include a review of HAZOP documentation. This project included the addition of 4 new SIFs. Professional 2021-02-12
Verified
Pending
Initial Assessment 
61511-FSA1 | Stage 1 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos UK, Simon has carried out several ad-hoc FSA1's as part of FSA5, albeit on very minor modifications, and generally only with impact on LOPA and SRS documentation rather than HAZOP/PHA documentation. As part of this role Simon has accepted many FSA1 reports for Petroineos. Simon has carried out 1 FSA1 in another role on behalf of a North Sea operator, which did include a review of HAZOP documentation. This project included the addition of 4 new SIFs. Professional 2021-02-12
Verified
Pending
Initial Assessment 
61511-DES H/W | Clause 11 - SIS Design and EngineeringMore informationAs Technical Authority and site FS Engineer at Petroineos, Simon was required to sign off and technically approve EC&I design for new and modified SIFs carried out by other engineers and third party EPCs. This included the detailed design of new logic solvers and SIS improvement project with a value up to £8M, and modifications on legacy SIFs up to SIL3. Simon has also been the Petroineos EC&I technical lead and project SIS owner on many SIS related projects. Simon has also carried out SIS design activities for smaller in-house projects featuring hardware and software changes. Predominantly this has been replacing older and obsolete field equipment with newer devices, often upgrading from discrete signals to analogue inputs. Simon has also specified field instruments and valves for use in SIF circuits. Master 2021-01-24
Verified
Pending
Initial Assessment 
61511-DES H/W | Clause 11 - SIS Design and EngineeringMore informationAs Technical Authority and site FS Engineer at Petroineos, Simon was required to sign off and technically approve EC&I design for new and modified SIFs carried out by other engineers and third party EPCs. This included the detailed design of new logic solvers and SIS improvement project with a value up to £8M, and modifications on legacy SIFs up to SIL3. Simon has also been the Petroineos EC&I technical lead and project SIS owner on many SIS related projects. Simon has also carried out SIS design activities for smaller in-house projects featuring hardware and software changes. Predominantly this has been replacing older and obsolete field equipment with newer devices, often upgrading from discrete signals to analogue inputs. Simon has also specified field instruments and valves for use in SIF circuits. Master 2021-01-24
Verified
Pending
Initial Assessment 
61511-DES H/W | Clause 11 - SIS Design and EngineeringMore informationAs Technical Authority and site FS Engineer at Petroineos, Simon was required to sign off and technically approve EC&I design for new and modified SIFs carried out by other engineers and third party EPCs. This included the detailed design of new logic solvers and SIS improvement project with a value up to £8M, and modifications on legacy SIFs up to SIL3. Simon has also been the Petroineos EC&I technical lead and project SIS owner on many SIS related projects. Simon has also carried out SIS design activities for smaller in-house projects featuring hardware and software changes. Predominantly this has been replacing older and obsolete field equipment with newer devices, often upgrading from discrete signals to analogue inputs. Simon has also specified field instruments and valves for use in SIF circuits. Master 2021-01-24
Verified
Pending
Initial Assessment 
61511-DES H/W | Clause 11 - SIS Design and EngineeringMore informationAs Technical Authority and site FS Engineer at Petroineos, Simon was required to sign off and technically approve EC&I design for new and modified SIFs carried out by other engineers and third party EPCs. This included the detailed design of new logic solvers and SIS improvement project with a value up to £8M, and modifications on legacy SIFs up to SIL3. Simon has also been the Petroineos EC&I technical lead and project SIS owner on many SIS related projects. Simon has also carried out SIS design activities for smaller in-house projects featuring hardware and software changes. Predominantly this has been replacing older and obsolete field equipment with newer devices, often upgrading from discrete signals to analogue inputs. Simon has also specified field instruments and valves for use in SIF circuits. Master 2021-01-24
Verified
Pending
Initial Assessment 
61511-SILV&C | SIL Verification and Calculation Master 2022-02-10
Verified
Pending
Initial Assessment 
61511-SILV&C | SIL Verification and Calculation Master 2022-02-10
Verified
Pending
Initial Assessment 
61511-SILV&C | SIL Verification and Calculation Master 2022-02-10
Verified
Pending
Initial Assessment 
61511-FAT/SAT | Clauses 13 / 15 - Factory Acceptance Test / SIS Safety ValidationMore informationSimon has carried out a number of FATs on new software based logic solvers to ensure that the software and hardware specifications have been met and the requirements of the SRS fully implemented. This work has been on Honeywell FSC and Safety Manager systems, and HIMA F35 systems. Simon also assisted with developing the use of test scripts to test all possible combinations of voted inputs, including all 125 cases for a 3 input vote. Simon has also carried out FAT on ball valve systems, UPS systems and electrical switchboards up to 11kV. Master 2021-05-09
Verified
Pending
Initial Assessment 
61511-FAT/SAT | Clauses 13 / 15 - Factory Acceptance Test / SIS Safety ValidationMore informationSimon has carried out a number of FATs on new software based logic solvers to ensure that the software and hardware specifications have been met and the requirements of the SRS fully implemented. This work has been on Honeywell FSC and Safety Manager systems, and HIMA F35 systems. Simon also assisted with developing the use of test scripts to test all possible combinations of voted inputs, including all 125 cases for a 3 input vote. Simon has also carried out FAT on ball valve systems, UPS systems and electrical switchboards up to 11kV. Master 2021-05-09
Verified
Pending
Initial Assessment 
61511-FSA2 | Stage 2 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried out a number of FSA2, either as stand alone FSA2 or as part of FSA5. These have generally been on installation of new SIFs to existing plants, or as significant modifications that warranted a FSA1,2,3 route rather than an FSA5 approach. This included logic solver upgrades and tankage high levels with run down intertrips. Simon has also verified and approved multiple FSA2 produced by EPC’s and SI’s for Petroineos, Incorporating both software and hardware. Simon also assisted with generation of Petroineos’s FSA2 checklists, and verification checklists. In other roles, Simon has carried out FSA2s for North Sea and onshore oil and gas operators. Master 2021-11-14
Verified
Pending
Initial Assessment 
61511-FSA2 | Stage 2 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried out a number of FSA2, either as stand alone FSA2 or as part of FSA5. These have generally been on installation of new SIFs to existing plants, or as significant modifications that warranted a FSA1,2,3 route rather than an FSA5 approach. This included logic solver upgrades and tankage high levels with run down intertrips. Simon has also verified and approved multiple FSA2 produced by EPC’s and SI’s for Petroineos, Incorporating both software and hardware. Simon also assisted with generation of Petroineos’s FSA2 checklists, and verification checklists. In other roles, Simon has carried out FSA2s for North Sea and onshore oil and gas operators. Master 2021-11-14
Verified
Pending
Initial Assessment 
61511-FSA2 | Stage 2 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried out a number of FSA2, either as stand alone FSA2 or as part of FSA5. These have generally been on installation of new SIFs to existing plants, or as significant modifications that warranted a FSA1,2,3 route rather than an FSA5 approach. This included logic solver upgrades and tankage high levels with run down intertrips. Simon has also verified and approved multiple FSA2 produced by EPC’s and SI’s for Petroineos, Incorporating both software and hardware. Simon also assisted with generation of Petroineos’s FSA2 checklists, and verification checklists. In other roles, Simon has carried out FSA2s for North Sea and onshore oil and gas operators. Master 2021-11-14
Verified
Pending
Initial Assessment 
61511-FSA2 | Stage 2 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried out a number of FSA2, either as stand alone FSA2 or as part of FSA5. These have generally been on installation of new SIFs to existing plants, or as significant modifications that warranted a FSA1,2,3 route rather than an FSA5 approach. This included logic solver upgrades and tankage high levels with run down intertrips. Simon has also verified and approved multiple FSA2 produced by EPC’s and SI’s for Petroineos, Incorporating both software and hardware. Simon also assisted with generation of Petroineos’s FSA2 checklists, and verification checklists. In other roles, Simon has carried out FSA2s for North Sea and onshore oil and gas operators. Master 2021-11-14
Verified
Pending
Initial Assessment 
61511-INSTALL | Clause 14 SIS Installation and CommissioningMore informationAs Technical Authority for Petroineos UK and previously as SIS Project Engineer for Petroineos Refinery, Simon has led the construction and commissioning phases of many SIS related projects up to the value of £8M. These projects ranged from the introduction of single new SIFs to existing systems to complete logic solver replacement projects. Simon has led the construction and commissioning teams, developing commissioning strategies & energisation plans for projects and formally accepted installation and commissioning as complete for major projects for Petroineos. In 2019 Simon wrote a new test & commissioning standard for all Petroineos UK sites following BS EN 62381-2012. Master 2021-05-09
Verified
Pending
Initial Assessment 
61511-FSA3 | Stage 3 Functional Safety AssessmentMore informationAt =Method and as Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA3’s, generally on smaller scope projects (<£1M spend). These projects included SIL1 and SIL 2 systems for tank overfill, intertips between units and tank farm, and environmental oil/water separation systems, including the installation of new hardware and new software systems. Master 2023-04-12
Verified
Pending
Initial Assessment 
61511-FSA3 | Stage 3 Functional Safety AssessmentMore informationAt =Method and as Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA3’s, generally on smaller scope projects (<£1M spend). These projects included SIL1 and SIL 2 systems for tank overfill, intertips between units and tank farm, and environmental oil/water separation systems, including the installation of new hardware and new software systems. Master 2023-04-12
Verified
Pending
Initial Assessment 
61511-FSA3 | Stage 3 Functional Safety AssessmentMore informationAt =Method and as Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA3’s, generally on smaller scope projects (<£1M spend). These projects included SIL1 and SIL 2 systems for tank overfill, intertips between units and tank farm, and environmental oil/water separation systems, including the installation of new hardware and new software systems. Master 2023-04-12
Verified
Pending
Initial Assessment 
61511-FSA3 | Stage 3 Functional Safety AssessmentMore informationAt =Method and as Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA3’s, generally on smaller scope projects (<£1M spend). These projects included SIL1 and SIL 2 systems for tank overfill, intertips between units and tank farm, and environmental oil/water separation systems, including the installation of new hardware and new software systems. Master 2023-04-12
Verified
Pending
Initial Assessment 
61511-FSA3 | Stage 3 Functional Safety AssessmentMore informationAt =Method and as Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA3’s, generally on smaller scope projects (<£1M spend). These projects included SIL1 and SIL 2 systems for tank overfill, intertips between units and tank farm, and environmental oil/water separation systems, including the installation of new hardware and new software systems. Master 2023-04-12
Verified
Pending
Initial Assessment 
61511-FSA3 | Stage 3 Functional Safety AssessmentMore informationAt =Method and as Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA3’s, generally on smaller scope projects (<£1M spend). These projects included SIL1 and SIL 2 systems for tank overfill, intertips between units and tank farm, and environmental oil/water separation systems, including the installation of new hardware and new software systems. Master 2023-04-12
Verified
Pending
Initial Assessment 
61511-O&M | Clause 16 SIS Operations and MaintenanceMore informationThroughout his time at Petroineos as asset care engineer, SIS engineer and E&I technical authority, Simon has managed all aspects of the operational & maintenance phase of the life-cycle. This included reworking of the refinery’s proof test template, and ensuring the proof tests coverage was as wide as possible. Latterly, Simon was responsible for approving new test procedures. Master 2021-05-09
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA4 | Stage 4 Functional Safety AssessmentMore informationAs Technical Authority for Petroineos and SIS Engineer, Simon has carried many FSA4’s either on new SIFs, 18 months after commissioning, SIFs installed earlier to IEC61511 standards, and on legacy systems up to SIL3. This has generally been a SIF by SIF approach, rather than unit wide or SIS approach. Simon also defined a legacy approach to FSA4 using the CDOIF installed system guidance, generating a legacy FSA4 checklist. Simon has trained and coached others to carry out FSA4 for Petroineos. In other roles, Simon has carried out FSA4s for North Sea and onshore oil and gas operators. Master 2021-02-24
Verified
Pending
Initial Assessment 
61511-FSA5 | Modification and Stage 5 Functional Safety Assessment Master 2022-02-10
Verified
Pending
Initial Assessment 
61511-FSA5 | Modification and Stage 5 Functional Safety Assessment Master 2022-02-10
Verified
Pending
Initial Assessment 

ECI

Task Level of
Competency
Date Verification
Status
ECI-CONTROL | Programming and control fundamentals Master 2022-02-10
Verified
Pending
Initial Assessment 
ECI-INST | Field devices - measurement principles and final elements Master 2022-02-10
Verified
Pending
Initial Assessment 
ECI-INST | Field devices - measurement principles and final elements Master 2022-02-10
Verified
Pending
Initial Assessment 
ECI-LVELEC | Electrical devices and systems <1kV Pending Review 2021-09-08
Verified
Pending
Initial Assessment 
ECI-HVELEC | Electrical devices and systems >1kV Pending Review 2021-09-08
Verified
Pending
Initial Assessment 
ECI-ATEX | ATEX instrumentation Master 2022-02-10
Verified
Pending
Initial Assessment 

ALARMS

Task Level of
Competency
Date Verification
Status
ALARM-PSD | Philosophy, Spec and Design Master 2020-12-22
Verified
Pending
Initial Assessment 
ALARM-PSD | Philosophy, Spec and Design Master 2020-12-22
Verified
Pending
Initial Assessment 
ALARM-IR | Implement & Rationalise Master 2020-12-22
Verified
Pending
Initial Assessment 
ALARM-ROMT | Response, O&M & Test Master 2020-12-22
Verified
Pending
Initial Assessment 

GENERAL

Task Level of
Competency
Date Verification
Status
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment 
GENERAL | Activities Relevant to multiple tasks Pending Review
Verified
Pending
Initial Assessment