=Method Group
More information about this page | Visit www.methodcompreg.com
This page is the public summary of the =Method account holder named above, showing the Tasks for which competency has been assessed and the associated status. Further detail on the Competency Register may be found at www.methodcompreg.com.
The =Method Competency register is based on the following key principles
* The Competency Register recognises that it is sometimes clear at interview that an account holder should be awarded a particular Task status, but it is not possible for them to provide evidence of projects completed with previous employers. This position is recognised by the
symbol – which indicates that the account holder needs to complete 4 peer reviewed projects which will be subject to additional scrutiny.
close popup
To access this account please enter the password below. this password will be available from Dr Jeni only.
| Task | Level of Competency |
Date | Verification Status |
| 61511-FSM | Functional Safety Management | Master | 2018-08-16 |
Pending
|
|
| Peer Reviewed Project |
P-2736. Checker of FS Audit of petrochemical plant FSM procedures. |
2022-05-20 |
|
| 61511-FSM | Functional Safety Management | Master | 2018-08-16 |
Pending
|
|
|
P-2074-2. FS Audit and Assessment of Dockyard Crane SIF design. Checker of report. |
2018-08-16 |
|
| 61511-SRS | Safety Requirement Specification | Master | 2021-03-05 |
Pending
|
|
| Peer Reviewed Project |
P-2584. Verification of SRS for pharmaceutical industry SIFs. |
2021-03-05 |
|
| 61511-FSA1 | Stage 1 Functional Safety Assessment | Master | 2022-08-19 |
Pending
|
|
| Peer Reviewed Project |
P-2831. FSA 1 of upgrade to offshore gas platform. Author of report. |
2022-11-01 |
|
| 61511-FSA1 | Stage 1 Functional Safety Assessment | Master | 2022-08-19 |
Pending
|
|
|
P-2705. FSA 1 of Steel Industry Continuous Annealing Process Line. Checker of report. |
2022-10-01 |
|
| 61511-FSA1 | Stage 1 Functional Safety Assessment | Master | 2022-08-19 |
Pending
|
|
|
P-2764. FSA 1 of offshore gas facility modification. Author of report. |
2022-07-27 |
|
| 61511-FSA1 | Stage 1 Functional Safety Assessment | Master | 2022-08-19 |
Pending
|
|
|
P-2573 FSA 1 of Scottish whisky industry tanker loading - checker of report |
2022-01-11 |
|
| 61511-FSA1 | Stage 1 Functional Safety Assessment | Master | 2022-08-19 |
Pending
|
|
|
P-2262. FSA 1 of emulsion plant for explosives manufacturer. Author of report. |
2019-01-29 |
|
| 61511-FSA1 | Stage 1 Functional Safety Assessment | Master | 2022-08-19 |
Pending
|
|
|
P-2141. FSA1 of Acid storage project. Checker of report. |
2018-07-09 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
| Peer Reviewed Project |
P-5029. To calculate an average Probability of Failure on Demand (PFDavg) for a complex SIF. Author of calculations. |
2021-10-17 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
|
P-2382. SIL V&C of terminal and tank storage application. Author of report. |
2020-06-05 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
|
P-2391C. SIL V&C for plastics manufacturer. Author of checklists and report. |
2020-02-27 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
|
P-2136. SIL Verification of SIFs for power generation project - conversion from coal to wood chip fuel. Author of report. |
2018-06-01 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
| Projects |
P-2673m. Providing advice on SIL verification of legacy SIF. |
2021-10-01 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
|
P-2584. FSA1 begun but abandoned following review that identified inherently safe alternative solution, not formally peer reviewed. |
2021-04-02 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
|
P-2263. SIL V&C of chemical plant SIF. Author of report. Project cancelled, so not promoted to Knowledge. |
2019-03-25 |
|
| 61511-SILV&C | SIL Verification and Calculation | Master | 2018-06-01 |
Pending
|
|
|
P-2193. SILV&C Checklists for Acid Storage project. No formal peer review, so activity not promoted to Peer reviewed Project. Checker of report. |
2019-01-24 |
|
| 61511-FSA2 | Stage 2 Functional Safety Assessment | Master | 2021-03-05 |
Pending
|
|
| Peer Reviewed Project |
P-2274. FSA 2 for precious metals recovery application (spray dryer). Author of report. |
2020-04-15 |
|
| 61511-FSA2 | Stage 2 Functional Safety Assessment | Master | 2021-03-05 |
Pending
|
|
|
P-2074-2. FSA 2 of crane safety system application. Checker of report. |
2018-07-01 |
|
| 61511-FSA2 | Stage 2 Functional Safety Assessment | Master | 2021-03-05 |
Pending
|
|
| Projects |
P-2021. FSA 2 report in to pharmaceutical industry tank storage application. Project not completed, so not promoted to Knowledge. Checker of report |
2018-12-16 |
|
| 61511-PRIOR USE | Prior Use Compliance Assessment | Master | 2017-06-26 |
Pending
|
|
| Peer Reviewed Project |
P-5012 Proven in use assessment of gate valve. Co-author and co-verifier of proven in use assessment report |
2020-08-17 |
|
| 61511-PRIOR USE | Prior Use Compliance Assessment | Master | 2017-06-26 |
Pending
|
|
|
P-5012. Proven in Use and Prior Use assessment, including FMEA and manufacturing assessment. Reviewed by HSE as part of close out of action legal. Author of Prior Use report. |
2020-06-02 |
|
| 61511-PRIOR USE | Prior Use Compliance Assessment | Master | 2017-06-26 |
Pending
|
|
|
P-2003. Prior use assessment of pilot burner from refinery. Author of report. |
2017-06-26 |
|
| 61511-PRIOR USE | Prior Use Compliance Assessment | Master | 2017-06-26 |
Pending
|
|
| Projects |
P-5032 Preliminary investigation to determine likelihood of success of a prior use assessment on waste industry SIF. |
2022-02-22 |
|
| 61511-FSA4 | Stage 4 Functional Safety Assessment | Professional | 2023-01-22 |
Pending
|
|
| 61511-FSA4 | Stage 4 Functional Safety Assessment | Professional | 2023-01-22 |
Pending
|
|
| 61511-FSA4 | Stage 4 Functional Safety Assessment | Professional | 2023-01-22 |
Pending
|
|
| Task | Level of Competency |
Date | Verification Status |
| 61508-FSM | Functional Safety Management | Master | 2018-10-31 |
Pending
|
|
| Deliver Training / Present Paper | P-2093. Design and delivery of workshop in 61508 compliance to gas detector supplier. | 2018-10-31 |
|
| 61508-FSM | Functional Safety Management | Master | 2018-10-31 |
Pending
|
|
| Peer Reviewed Project | P-2088. Author of FSM (CASS) assessment of systems integrator commissioned by end user. Checker of report. | 2018-01-01 |
|
| 61508-FSM | Functional Safety Management | Master | 2018-10-31 |
Pending
|
|
| P-2103. Assessment and certification of 4-20mA pressure transmitter. Checker of report. | 2017-09-20 |
|
| 61508-FSM | Functional Safety Management | Master | 2018-10-31 |
Pending
|
|
| Projects | P-2089. Delivery of workshop related to assessment of pressure transmitter compliance with IEC 61508, including review of approach to FSM. | 2017-08-25 |
|
| 61508-PART2 | (Hardware) Requirements for E/E/PE Safety-Related Systems | Master | 2018-10-31 |
Pending
|
|
| Deliver Training / Present Paper | P-2093. Design and delivery of workshop in 61508 compliance to gas detector supplier. | 2018-10-31 |
|
| 61508-PART2 | (Hardware) Requirements for E/E/PE Safety-Related Systems | Master | 2018-10-31 |
Pending
|
|
| Peer Reviewed Project | P-2103. Assessment and certification of 4-20mA pressure transmitter. Checker of report. | 2017-09-29 |
|
| 61508-PART2 | (Hardware) Requirements for E/E/PE Safety-Related Systems | Master | 2018-10-31 |
Pending
|
|
| Projects | P-2089. Delivery of workshop related to assessment of pressure transmitter compliance with IEC 61508, including review of approach based on 61508-2. | 2017-08-25 |
|
| 61508-FMEADEV | Failure Modes and Effects Analysis (Device level) | Master | 2020-06-09 |
Pending
|
|
| Peer Reviewed Project | P-5012. Proven in Use assessment, including FMEA and manufacturing assessment. Reviewed by HSE as part of close out of action legal. Checker of FMEA. | 2020-06-09 |
|
| 61508-PIU | Route 2 Compliance Assessment | Master | 2017-07-03 |
Pending
|
|
| Peer Reviewed Project | P-5026. Proven in use compliance assessment for electric actuator. Author. | 2021-05-20 |
|
| 61508-PIU | Route 2 Compliance Assessment | Master | 2017-07-03 |
Pending
|
|
| P-5012. Proven in Use assessment, including FMEA and manufacturing assessment. Reviewed by HSE as part of close out of action legal. Author of PiU report. | 2020-06-09 |
|
| 61508-PIU | Route 2 Compliance Assessment | Master | 2017-07-03 |
Pending
|
|
| P-2103. Assessment and certification of 4-20mA pressure transmitter. Author of report. | 2017-09-20 |
|
| 61508-PIU | Route 2 Compliance Assessment | Master | 2017-07-03 |
Pending
|
|
| P-2003. Proven in Use assessment of pilot burner - checker of FMEA and author of report analysing returns data. | 2017-07-03 |
|
| 61508-PIU | Route 2 Compliance Assessment | Master | 2017-07-03 |
Pending
|
|
| Projects | P-2089. Delivery of workshop related to assessment of pressure transmitter compliance with IEC 61508, including review of approach based on Proven in Use. | 2017-08-25 |
|
| Task | Level of Competency |
Date | Verification Status |
| HRA-LOPA | Layer of Protection Analysis | Master | 2013-01-01 |
Pending
|
|
| Peer Reviewed Project |
P-6120. LOPA study of Low Waste Gas hazard scenario in a steel industry application. Verifier of study report. |
2022-05-17 |
|
| HRA-LOPA | Layer of Protection Analysis | Master | 2013-01-01 |
Pending
|
|
|
P-6127. LOPA of tank storage application, base on "typicals" approach. Verifier of report. |
2022-05-09 |
|
| HRA-LOPA | Layer of Protection Analysis | Master | 2013-01-01 |
Pending
|
|
|
P-6113. Updating the LOPA studies done for tanker bottom loading, providing a table of standard ignition probability values applicable to ethanol and updating client risk matrix. Verifier. |
2021-12-09 |
|
| HRA-LOPA | Layer of Protection Analysis | Master | 2013-01-01 |
Pending
|
|
|
P-6069. Layer of Protection Analysis (LOPA) study on steel plant continuous annealing process. Verifier of study report. |
2021-06-24 |
|
| HRA-LOPA | Layer of Protection Analysis | Master | 2013-01-01 |
Pending
|
|
|
P-2497. Providing Process and Functional Safety consultancy and guidance for a Floodgate Controller project. Verifier. |
2021-01-01 |
|
| HRA-LOPA | Layer of Protection Analysis | Master | 2013-01-01 |
Pending
|
|
| Task Relevant Training (no exam) |
SafetTech Engineering LOPA Training Course |
2013-01-01 |
|
| HRA-HAZOP | Hazard and Operability Study | Professional | 2022-08-18 |
Pending
|
|
| Peer Reviewed Project | P-6168. Update to HazOp and LOPA studies for storage tanks due to site extension. Verifier of study report. | 2022-09-30 |
|
| HRA-HAZOP | Hazard and Operability Study | Professional | 2022-08-18 |
Pending
|
|
| P-6143A. HazOp of steel industry Blast Furnace Gas Distribution System. Verifier (mentored) of study report. | 2022-09-30 |
|
| HRA-HAZOP | Hazard and Operability Study | Professional | 2022-08-18 |
Pending
|
|
| Projects | First experience was 'on-the-job' training about twenty years ago when I secretaried HazOps for some nuclear and wind projects. Not had formal training just on HazOp, although it has come up in the content of a couple of training courses I think. Apart from that I was secretary at a couple of for ERA and then the FSA1/HazOp review work that I have done for =M. | 2022-08-17 |
|
| HRA-HS2 | Hazard Identification and Understanding | Master | 2021-12-30 |
Pending
|
|
| Projects | Activities recorded for 2017 date in HRA-HS0/1 also included HS2, not repeated here, but are relevant to HRA-HS2. | 2017-01-01 |
|
| HRA-HS2 | Hazard Identification and Understanding | Master | 2021-12-30 |
Pending
|
|
| HS2/3 for the trials and training facilities at the QinetiQ Farnborough site, such as the Man Carrying Centrifuge and the 5m Wind Tunnel. (2 year project). | 2014-01-01 |
|
| HRA-HS0/1 | Inherent Safety and Initial Hazard Review | Master | 2021-12-30 |
Pending
|
|
| Projects | P-6122mB. Feedback on HS1 for Steel Industry axial steam engine application. | 2022-01-19 |
|
| HRA-HS0/1 | Inherent Safety and Initial Hazard Review | Master | 2021-12-30 |
Pending
|
|
| P-6122mA. Feedback on HS1 for Steel Industry flare gas application. | 2022-01-11 |
|
| HRA-HS0/1 | Inherent Safety and Initial Hazard Review | Master | 2021-12-30 |
Pending
|
|
| HS0/1/2 for the Project Marshall upgrade of MoD Air Traffic Management capabilities at all MoD operated sites in the UK and overseas. (Project still ongoing in December '21). | 2017-01-01 |
|
| HRA-HS0/1 | Inherent Safety and Initial Hazard Review | Master | 2021-12-30 |
Pending
|
|
| HS0/1/2 activities for the tlm Nexus Carbon/Resolve software product as utilised by the UK MoD Typhoon team. | 2017-01-01 |
|
| HRA-HS0/1 | Inherent Safety and Initial Hazard Review | Master | 2021-12-30 |
Pending
|
|
| Jeni lead an evaluation of the resultant risk from fire and explosion hazards on the Airseeker platform. Activities included liaising with the UK MoD project team to determine relevant information, evaluation of that information against the extant risk assessment and reporting of information within the hazard assessment documentation. | 2017-01-01 |
|
| Task | Level of Competency |
Date | Verification Status |
| PS-HAZARD | Process Hazard Knowledge | Professional | 2021-12-30 |
Pending
|
|
| Projects | Jeni has background knowledge of process hazards and much experience of hazards associated with work in the military and defence fields, carrying out hazard studies based on FMEA and SWIFT techniques. Jeni has limited experience of process hazards associated with general process industries. | 2021-12-30 |
|
| Task | Level of Competency |
Date | Verification Status |
| FS-APPROVE | Approval of FS related documentation | Master | 2022-10-31 |
Pending
|
|
| Informal Training |
Jeni reviewed requirements for FS-APPROVE with JS and SE (both of whom hold MST status for this competency task). |
2022-05-10 |
|
| FS-APPROVE | Approval of FS related documentation | Master | 2022-10-31 |
Pending
|
|
| Peer Reviewed Project |
P-2736. FS Audit. Approval of audit reports. |
2022-06-30 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Deliver Training / Present Paper | IET International Conference on System Safety and Cyber Security (2014). Safety Assessment of Smart Instruments for the Nuclear Industry. | 2014-10-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Civil-Comp Press - Conference on Computational Structures Technology. Risk modelling of fires and explosions in offshore platform modules. | 2006-09-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| IMechE Proceedings of the Institution of Mechanical Engineers, Part O : Journal of Risk and Reliability. Risk modelling of fires and explosions in open-sided offshore platform modules | 2006-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Advances in Reliability Technology Symposium (ARTS) conference.Risk modelling of fires and explosions in open-sided offshore platform modules. | 2005-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Examination / Qualification | IET Chartered Engineer | 1999-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Loughborough University - BEng Mathematical Engineering. | 1999-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Loughborough University (and Mobil NS Ltd) - PhD Risk and Reliability Engineering | 1999-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Peer Reviewed Project | P-5024. Outside scope of competency register. Evaluation of impact of safety fault on fire door. Providing expert guidance on strategy and requirements of product recall. | 2021-02-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| P-5017. Project outside scope of competency register. Author: Evaluation of the impact of an increased product failure rate on the likelihood of fatality resulting from a fire. Cost benefit analysis to determine at what point it can no longer be argued that implementing a programme or replacement of the suspected faulty product is grossly disproportionate. Estimate of required test periodicity for the product dependent on the system PFD required by the end-user. Checker: Validation of risk model, cost benefit analysis and test period calculations through review of input data, calculations and comparison of output with related project experience. | 2021-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| P-5001. Project outside scope of competency register. Review of warranty returns for fire and gas detector supplier - determining "action" levels for remedial action based on number of returns. Author of report. | 2019-03-29 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Task Relevant Training (exam) | TUV Sud 61511 Functional Safety Professional. | 1999-01-01 |
|
| GENERAL | Activities Relevant to multiple tasks | Pending Review | 2019-03-29 |
Pending
|
|
| Task Relevant Training (no exam) | DNV - MoD Ship Safety Management Course (SSMO) | 1999-01-01 |
|